A photo of the inside of the building looking from the filter gallery over the clarifier basins.
The filter presses were set above the unloading garage and the final roof panels have been installed. Here is a picture of the lime silos installed in the chemical garage.
The masonry work inside is progressing and several walls have been installed.
The east abutment of the bridge was completed and installation of the gabion baskets began along the east side of the channel. Just the first peices of the forms for the bridge deck have been set and the contractor has been off-site over the holidays.