Thursday, October 10, 2019

Winnebago Avenue Reconstruction

The contractor was able to get all the aggregate hauled on Phase 1 and is beginning removals of Phase 2. Traffic will be shifting to the east entrance/exit of Fairmont Estates, the mobile home park, as this work begins today. The removals will be completed and new watermain will be installed up to TH 15. The street will be kept to a gravel surface to allow for access to Bean Town and The Ranch during this work. Concrete work is anticipated to begin the week of the 14th.

Tuesday, October 8, 2019

Winnebago Avenue Reconstruction

Poor weather and poor sub-grade soils and created delays in finishing Phase 1. The contractor is hauling aggregate today and tomorrow to get the surfacing on Phase 1 ahead of the forecast weather the end of this week.

Resurface and Overlay Projects

The contractor has completed the sub-grade work on Lynn and Burton. Both of those projects have been delayed by the weather and should be getting the concrete work done in the next week. Following the concrete replacements, the contractor plans to get those two projects paved and finished.

The 4th Street project is scheduled to start the end of this week, 10/10 or 10/11. However, the weather forecast does not look very favorable. If the forecast holds, the contractor will likely begin work on Monday. The first phase of this project will be to complete some storm sewer work in the alley west of TH 15 adjacent to Century 21. Fourth Street will be closed between TH 15 and Fairview during this work phase.