Friday, March 15, 2013

Lair Road Bridge

The bridge deck was poured January 11th.



Here is a photo of the rebar prior to the installtion of the concrete for the new railing. The railings have since been cast and the forms removed.



Below is a photo from under the new bridge looking south at the existing bridge. The widening of the navigation channel is shown. This photo also shows the new concrete railing.

Water Treatment Plant

Equipment installation continues inside. Below is a picture of the lime solids contact chambers. These basins are 18' deep and will be the first process for the water treatment in the new plant.



Contractor has installed the lime slaking units. These handle the lime material that is added to the raw water to remove hardness and other materials.



Numerous chemical tanks, mechanical equipment, electrical equipment, and plumbing is being installed around the plant. Here are a few snapshots.

Friday, January 4, 2013

Water Treatment Plant

A photo of the inside of the building looking from the filter gallery over the clarifier basins.



The filter presses were set above the unloading garage and the final roof panels have been installed. Here is a picture of the lime silos installed in the chemical garage.



The masonry work inside is progressing and several walls have been installed.



Lair Road Bridge

The east abutment of the bridge was completed and installation of the gabion baskets began along the east side of the channel. Just the first peices of the forms for the bridge deck have been set and the contractor has been off-site over the holidays.









Monday, December 3, 2012

Water Treatment Plant

Installation of the windows is progressing quickly. Here is an exterior photo of some of the new glass.



The precast contractor has spent the last three weeks installing precast walls and hollowcore floor sections in the remainder of the plant. They also are installing the precast columns and beams for the chemical unloading garage.







Here is a view down into the new clarifier tanks and sludge basins.



Demolition of the deep intake structure is complete and the new shallow intake structure is currently operating and feeding the existing water treatment plant.



Lair Road Bridge

The west abutment concrete is nearly complete with the wingwall on the south side and the combination wingwall/retaining wall on the north. Here is a photo of the abutment and retaining wall.



Channel excavation has begun and placement of the new gabion baskets started last Friday. Here is a photo of the channel after the old riprap was removed.



Here is an aerial of the construction site taken on November 19, 2012.



Thursday, November 1, 2012

Lair Road Bridge

The concrete work has begun. Here is a photo of the first pour of concrete for the west abutment footing on October 26th.



Below is the steel rebar installed for the pier cap, with a photo of the completed pier cap as well.





The contractor has started forming and placing steel for the west abutment and wingwalls.