The water treatment plant started sending out finished water to the distribution system about two weeks ago. All the systems are running as expected and the contractor is working to finish up the interior spaces as well as starting on some punch list items. The parking lots have been completed and landscaping will begin shortly. The project is scheduled for substantial completion in mid-October. Here are some interior pictures of the operator's room, solids contact basin, softening room, and entry.
Friday, September 20, 2013
Lair Road Bridge
Lair Road is complete and the street was opened in mid-July. Seeding was completed and a new split rail fence was installed on either side of the channel. The City held a ribbon cutting ceremony on September 13th. The contractor has a couple railing items to finish out this fall and then we will be able to close out this project. Here is an overhead of the finished project.
Friday, June 28, 2013
Airport Construction
The work on the City's airport has been underway for a month or so now. Even with the persistent rain in June they have made progress. The main taxiway has been overlaid with new asphalt and a portion of the apron was milled and overlaid. The main runway 13/31 will be closing next week July 1 and the main taxiway will serve as the temporary runway for daily operations. No night landings will be allowed on the temporary runway.
Elm Street Construction
Elm Street reconstruction is ongoing from 1st Street to the railroad tracks. All existing street has been removed and many houses have been running off temporary water with the removals of the existing sanitary and water main. All new sanitary and water main is now installed from 1st Street to 3rd Street. These houses should have normal water service restored within a week or so. The residents north of 3rd will soon be contacted about having there water set up for temporary service as well. The intersection of 4th Street and Elm is closed and will be at least until the 4th of July. The detour is set up to have traffic use 3rd street as the east/west crossing point of Elm. Here are a couple construction photos.
Water Treatment Plant
Site work has been going the past few weeks, getting the base for the parking and driving lanes installed. The exterior stone is nearly finished with the exception of the entry area. This area was framed and the slab has been poured. The remaining storefront windows and stone will be installed in the coming weeks. The interior of the building is taking shape with offices being painted and cabinets installed. Testing and start-up of numerous pieces of equipment is ongoing. Equipment training for City Staff began last week and will continue for several weeks. The rain garden on the south side of the building has been graded and most of the storm sewer is installed. Here are some photos.
Lair Road Bridge
The navigation channel is open. Street work has been ongoing in between the rain these past few weeks. The final driving surface of the bridge was completed. The bridge has been painted and portions of the railing were installed this week. Concrete flatwork on Lair Road began this week and will continue next week. Lair Road will not be open for the 4th of July weekend, but the intersection of Lair and Shoreacres will be opened temporary for the holiday weekend. The intersection will close again on July 8th. Here is a picture of the bridge looking north.
Friday, March 15, 2013
2013 Improvement Projects
Here is a list of the streets planned for improvement in 2013 within the City. These projects will be assessed to the abutting property owner per the City's assessment policy.
RECONSTRUCTION
Project No. 13001-Elm Street; from First Street to Railroad tracks
RESURFACING
Project No. 13002-Cardinal Street; Prairie Avenue to Charles Street
Project No. 13003-Cedar Park Road; Lake Aires Road to Arthur Street
Project No. 13004-Roland Avenue; East Interlaken Road to Dorothy Street
Project No. 13005-Southwood Drive; Cottage Street to dead end
OVERLAYS
Project No. 13007-Parkwood Place from East Amber Lake Drive to dead end
SEAL COATS
Main Street; Railroad tracks to Lincoln Park
Lake Avenue, Bike Shoppe to Fourth Street
Torgerson Drive; TH15 to dead end
Hengen Street; 100’ west of Geraldine Street to dead end
Street Department parking lot
Geraldine Street; Martin Street to Hengen Street
Martin Street; Geraldine Street to Valley View Courts
Stella Court; Dead end to De-Lu Street
Sylvan Drive; Cottage Street to Cottage Street
Sylvia Street; East Belle Vue Road to Stade Lane
North & South Valley View Courts; south end to north end
Victoria Street; State Street to Burton Lane
Cory Lane; Dead end to Lake Avenue
South Armstrong Drive; Deadend to Lake Avenue
Albion Avenue; Government Street to West Belle Vue Road
Lincoln Park
Dorothy Street; Roland Avenue to dead end
Poetter’s Circle; Dorothy Street to dead end
Third Street; Park Street to Prairie Avenue
Fourth Street; TH15 to end of bituminous paving
Adams Avenue; TH15 to Home Street
Cadillac Avenue; Lair Road to Lakeview Street
Christina Street; North Avenue to Elm Street
Patriot Drive; Knollwood Drive to dead end
Albion Bike Trail; Interlaken Road to De-Lu Street
Cedar Creek Park Trails
City Parking Lot D; Park Street and Fourth Street
RECONSTRUCTION
Project No. 13001-Elm Street; from First Street to Railroad tracks
RESURFACING
Project No. 13002-Cardinal Street; Prairie Avenue to Charles Street
Project No. 13003-Cedar Park Road; Lake Aires Road to Arthur Street
Project No. 13004-Roland Avenue; East Interlaken Road to Dorothy Street
Project No. 13005-Southwood Drive; Cottage Street to dead end
OVERLAYS
Project No. 13007-Parkwood Place from East Amber Lake Drive to dead end
SEAL COATS
Main Street; Railroad tracks to Lincoln Park
Lake Avenue, Bike Shoppe to Fourth Street
Torgerson Drive; TH15 to dead end
Hengen Street; 100’ west of Geraldine Street to dead end
Street Department parking lot
Geraldine Street; Martin Street to Hengen Street
Martin Street; Geraldine Street to Valley View Courts
Stella Court; Dead end to De-Lu Street
Sylvan Drive; Cottage Street to Cottage Street
Sylvia Street; East Belle Vue Road to Stade Lane
North & South Valley View Courts; south end to north end
Victoria Street; State Street to Burton Lane
Cory Lane; Dead end to Lake Avenue
South Armstrong Drive; Deadend to Lake Avenue
Albion Avenue; Government Street to West Belle Vue Road
Lincoln Park
Dorothy Street; Roland Avenue to dead end
Poetter’s Circle; Dorothy Street to dead end
Third Street; Park Street to Prairie Avenue
Fourth Street; TH15 to end of bituminous paving
Adams Avenue; TH15 to Home Street
Cadillac Avenue; Lair Road to Lakeview Street
Christina Street; North Avenue to Elm Street
Patriot Drive; Knollwood Drive to dead end
Albion Bike Trail; Interlaken Road to De-Lu Street
Cedar Creek Park Trails
City Parking Lot D; Park Street and Fourth Street
Subscribe to: