Wednesday, January 11, 2012

Water Treatment Plant

After taking the week between Christmas and New Year's off the contractors are back to work. The weather has cooperated up until today as temperatures begin to fall and the talk of snow is in the forecast. Yesterday about 70' of wall was poured with another concrete pour scheduled for Friday of this week. Material continues to arrive and is being stored on-site. Some of the material includes, steel rebar, ductile iron piping, ductile iron pipe sleeves, and other miscellaneous pipe fittings.