The concrete curb and gutter has been installed and a portion of the asphalt paving has been completed. The ag lime has been installed as well as all of the lights for the complex. The contract to construct the concession, restroom, and storage building was just awarded and construction on that will begin in the next few weeks. Below is an aerial of the site as it starts to take shape.