Water Treatment Plant

A lot of progress has been made since the last post. Several hundred more yards of concrete have been placed in the filters and recarbonation basins. All of the flooring in the garage was placed along with the diesel tank for the new generator. This week the precast walls of the north half of the building were erected. The high service pumps and much more process piping was installed and precast hollow core flooring was set for a portion of the operations level.