Water Treatment Plant

Concrete is being poured on the south side of the building for the solids contact clarifiers and the lime sludge basins. Several loads of precast walls and hollow core panels were installed in the last month. Here is a photo looking down in the filter area and you can see the 100' long precast double tee sections which span this area.



Also the filter troughs were set in both the convetional and GAC filters.



Below is a picture from inside the building on the operating level. This area will ultimately become the operators room, lab, offices, conference room, and break room.