Winnebago Avenue Reconstruction

The contractor was able to get all the aggregate hauled on Phase 1 and is beginning removals of Phase 2. Traffic will be shifting to the east entrance/exit of Fairmont Estates, the mobile home park, as this work begins today. The removals will be completed and new watermain will be installed up to TH 15. The street will be kept to a gravel surface to allow for access to Bean Town and The Ranch during this work. Concrete work is anticipated to begin the week of the 14th.