Thursday, October 10, 2019
Winnebago Avenue Reconstruction
The contractor was able to get all the aggregate hauled on Phase 1 and is beginning removals of Phase 2. Traffic will be shifting to the east entrance/exit of Fairmont Estates, the mobile home park, as this work begins today. The removals will be completed and new watermain will be installed up to TH 15. The street will be kept to a gravel surface to allow for access to Bean Town and The Ranch during this work. Concrete work is anticipated to begin the week of the 14th.
Tuesday, October 8, 2019
Winnebago Avenue Reconstruction
Poor weather and poor sub-grade soils and created delays in finishing Phase 1. The contractor is hauling aggregate today and tomorrow to get the surfacing on Phase 1 ahead of the forecast weather the end of this week.
Resurface and Overlay Projects
The contractor has completed the sub-grade work on Lynn and Burton. Both of those projects have been delayed by the weather and should be getting the concrete work done in the next week. Following the concrete replacements, the contractor plans to get those two projects paved and finished.
The 4th Street project is scheduled to start the end of this week, 10/10 or 10/11. However, the weather forecast does not look very favorable. If the forecast holds, the contractor will likely begin work on Monday. The first phase of this project will be to complete some storm sewer work in the alley west of TH 15 adjacent to Century 21. Fourth Street will be closed between TH 15 and Fairview during this work phase.
The 4th Street project is scheduled to start the end of this week, 10/10 or 10/11. However, the weather forecast does not look very favorable. If the forecast holds, the contractor will likely begin work on Monday. The first phase of this project will be to complete some storm sewer work in the alley west of TH 15 adjacent to Century 21. Fourth Street will be closed between TH 15 and Fairview during this work phase.
Friday, September 20, 2019
Resurface and Overlay Projects
The contractor worked on Lynn Street this week and was able to get all removals complete, drain tile installed, and the surface brought back to a gravel driving surface. All residents, including Becky Lane, should have access to their driveways by the end of today. The contractor will now be moving to Burton Lane. They will be starting removals on Monday.
Tuesday, September 17, 2019
New pioneer pedestrian bridge
The contractor set the new pioneer pedestrian bridge today between Lake Sisseton and Lake George. The project is still under construction and the bridge is currently closed to pedestrian traffic. Stay tuned for the opening of the newest addition to the City’s trail system.
Winnebago Avenue Reconstruction
The contractor is installing drain tile on phase 1 of the project and will soon start placing the aggregate surface. With good weather, we are hoping to be moving into phase 2 in the next two weeks. When phase 2 begins, traffic control and access to the Five Lakes cooperative mobile home park will be moved to the east entrance. Stay tuned for further information on when that change will occur.
Resurface and Overlay projects
The contractor was able to get started on these projects after last weeks rains. They are completing some storm sewer work on the end of Hengen Street today. The contractor plans to move into Lynn Street on Wednesday, Sept. 18th. They will begin the removal process and access to the homes on Lynn and Becky will be restricted in the next day or two. Please be careful around the construction and plan ahead for access restrictions. Contact City Hall if you have questions about access.