Thursday, November 1, 2012

Water Treatment Plant

Concrete is being poured on the south side of the building for the solids contact clarifiers and the lime sludge basins. Several loads of precast walls and hollow core panels were installed in the last month. Here is a photo looking down in the filter area and you can see the 100' long precast double tee sections which span this area.



Also the filter troughs were set in both the convetional and GAC filters.



Below is a picture from inside the building on the operating level. This area will ultimately become the operators room, lab, offices, conference room, and break room.




Winnebago Avenue Sports Complex

The remainder of the asphalt paving was completed and striping was added for the parking lot. The ball fields and the concession stand have been completed. Portions of the site will be overseeded for the winter. Here are a couple pictures of the improvements.





Monday, October 1, 2012

Water Treatment Plant

All of the concrete walls for the filters are now complete. Concrete is being cast for the new clarifiers and footings for the chemical unloading garage are being formed. The block for the new shallow intake portion of the plant have been installed on the back side of the existing plant and this addition is visible from the lake side. Electrical, mechanical, and plumbing contractors are working all around the plant to install miles of wiring, duct work and process piping. Here are a couple of photos showing the wall of steel being tied for the new clarifier basins and a photo of the south side of the building with the elevator shaft on the left side of the picture.





Lair Road Bridge

The existing home was removed in mid-September along with several trees. The boat navigation channel was closed on September 24th and will remain closed until May 2013. The contractor began driving past last friday. Here is a picture of the second pile being driven on September 28th.



The pile driving continued this morning. When the contractor is done, there will be 52 pipe piles each driven to a depth of approximately 100' which will suuport the new bridge and retaining wall. Below is a picture of the west abutment pile as they are being installed.


Friday, August 31, 2012

Winnebago Avenue Sports Complex

The bases were installed this week on the fields and bollards were installed at all trail entrances. Doors have been installed on the concession stand with the outside concrete apron being poured this week. The contractor was installing the ceiling in all the rooms and all of the plumbing is ready for new fixtures.

Water Treatment Plant

A lot of progress has been made since the last post. Several hundred more yards of concrete have been placed in the filters and recarbonation basins. All of the flooring in the garage was placed along with the diesel tank for the new generator. This week the precast walls of the north half of the building were erected. The high service pumps and much more process piping was installed and precast hollow core flooring was set for a portion of the operations level.



Lair Road Bridge

The bids were opened for the construction of the new bridge. Minnowa Construction from Harmony, MN was awarded the project with a cost of $2.3 million. Construction is scheduled to begin in September beginning with the demolition of the existing house.