Pages

Thursday, January 15, 2015

Woodland Channel Construction

Construction has begun on the woodland channel project. This project will upgrade and re-align the navigation channel under Bird’s Bridge on Woodland Avenue. Traffic control is set up to maintain two-way traffic through the project with reduced lane widths. Please use caution when travelling through the construction zone. The project is anticipated to be open to boat traffic this spring and fully completed by mid-summer. Please contact tnemmers@fairmont.org with any questions.

Thursday, December 11, 2014

Albion Avenue Reconstruction

The street was opened to two-way traffic over the Thanksgiving weekend. The west side curb and gutter was not able to be installed due to the change in weather. This area has been barricaded to keep traffic away from the low shoulder that will be there for the rest of the winter. Construction speed limits are still in place due to the road not having curb and gutter on the west side. Temporary driveways have been constructed at all driveway locations. The remainder of the work will be completed in the Spring beginning as soon as the weather allows. Below is the December newsletter for this project. Thanks to everyone that has been impacted by this project for their understanding and continued patience with this important project.

Monday, November 10, 2014

Albion Avenue Reconstruction

The paving contractor worked through the weekend to get the southbound lanes poured ahead of the cold weather this week. With the weather turning poor, the progress of the project is being evaluated and will likely not get completed this fall. We will be coordinating with the general contractor on when to open up the project for two-way traffic and working to provide driveway access for the residents and businesses through the winter. A further update will be provided when those specifics are determined.

Friday, October 3, 2014

Albion Avenue Reconstruction

Construction continues to progress on the project. See the newsletter below with information. If you are having difficulty reading the newsletter please visit the City's website to view the original PDF file under news and announcements.

http://www.fairmont.org/news-announcements/

Friday, September 26, 2014

Albion Avenue Reconstruction

Concrete paving began this morning at 7am. The sub-contractor for paving is Doyle Conner which is based in Rochester. Here is a look down the street at the grade with all of the dowel baskets set in place for each transverse joint. The second picture shows how the concrete is placed on grade ahead of the paving machine. Lastly, is a photo of first concrete placed this morning. The contractor will be paving approximately 850 cubic yards today.

Thursday, September 25, 2014

Albion Avenue Reconstruction

Expect delays as paving of Albion Avenue between Lair Raid and Oak Beach Drive is scheduled for Friday, September 26th. Paving operations will be restricting traffic flow for most of the day and into the evening hours. These operations will cause significant delays so the public is encouraged to find an alternate route this day. Southbound traffic will still be able to access residences and businesses, but delays are anticipated, so please plan ahead. The southbound only traffic and business access will resume on Monday with the same restrictions as the past several weeks. Below is a picture of the northbound lane that will be paved on Friday.



Friday, August 22, 2014

Water Treatment Plant

Work continues on the old water treatment plant site. The contractor is working on reconstructing the shoreline along Budd Lake. A driveway and parking area will be installed later this year. In addition, the landscaping contractor will be onsite this fall to complete the final restoration of this site as well as the new water treatment plant site. Here is a picture of a concrete retaining wall along the shore of Budd Lake.