Tuesday, November 29, 2011
Water Treatment Plant
The weather continues to cooperate as the construction continues. The second half of the basin floor will be poured on Wednesday. The contractor is estimating 600 cubic yards of concrete will be placed that day.
Wednesday, November 23, 2011
Water Treatment Plant
Over 500 cubic yards of concrete were placed this morning as one-half of the base slab will be complete by the end of the day. Construction continues on schedule with another 500+ cubic yard concrete pour set for the middle of next week.
Winnebago Ave Sports Complex
The site has been seeded and mulched for the winter. The City will be obtaining bids for the lighting and restrooms this winter. Construction will resume next spring when the rest of the project will be completed.
Tuesday, November 8, 2011
Winnebago Ave Sports Complex
The site has been graded and 90% of the storm sewer has been installed. The parking lots are near finished grades and will be touched up prior to paving next spring. The site is currently being seeded and mulched.
Water Treatment Plant
The first concrete was poured yesterday. Construction is progressing as planned. The underdrain system is being installed with more concrete planned to be poured next week.