Installation of the windows is progressing quickly. Here is an exterior photo of some of the new glass.
The precast contractor has spent the last three weeks installing precast walls and hollowcore floor sections in the remainder of the plant. They also are installing the precast columns and beams for the chemical unloading garage.
Here is a view down into the new clarifier tanks and sludge basins.
Demolition of the deep intake structure is complete and the new shallow intake structure is currently operating and feeding the existing water treatment plant.
Monday, December 3, 2012
Lair Road Bridge
The west abutment concrete is nearly complete with the wingwall on the south side and the combination wingwall/retaining wall on the north. Here is a photo of the abutment and retaining wall.
Channel excavation has begun and placement of the new gabion baskets started last Friday. Here is a photo of the channel after the old riprap was removed.
Here is an aerial of the construction site taken on November 19, 2012.
Channel excavation has begun and placement of the new gabion baskets started last Friday. Here is a photo of the channel after the old riprap was removed.
Here is an aerial of the construction site taken on November 19, 2012.
Subscribe to:
Posts (Atom)