Thursday, October 10, 2019
Winnebago Avenue Reconstruction
The contractor was able to get all the aggregate hauled on Phase 1 and is beginning removals of Phase 2. Traffic will be shifting to the east entrance/exit of Fairmont Estates, the mobile home park, as this work begins today. The removals will be completed and new watermain will be installed up to TH 15. The street will be kept to a gravel surface to allow for access to Bean Town and The Ranch during this work. Concrete work is anticipated to begin the week of the 14th.
Tuesday, October 8, 2019
Winnebago Avenue Reconstruction
Poor weather and poor sub-grade soils and created delays in finishing Phase 1. The contractor is hauling aggregate today and tomorrow to get the surfacing on Phase 1 ahead of the forecast weather the end of this week.
Resurface and Overlay Projects
The contractor has completed the sub-grade work on Lynn and Burton. Both of those projects have been delayed by the weather and should be getting the concrete work done in the next week. Following the concrete replacements, the contractor plans to get those two projects paved and finished.
The 4th Street project is scheduled to start the end of this week, 10/10 or 10/11. However, the weather forecast does not look very favorable. If the forecast holds, the contractor will likely begin work on Monday. The first phase of this project will be to complete some storm sewer work in the alley west of TH 15 adjacent to Century 21. Fourth Street will be closed between TH 15 and Fairview during this work phase.
The 4th Street project is scheduled to start the end of this week, 10/10 or 10/11. However, the weather forecast does not look very favorable. If the forecast holds, the contractor will likely begin work on Monday. The first phase of this project will be to complete some storm sewer work in the alley west of TH 15 adjacent to Century 21. Fourth Street will be closed between TH 15 and Fairview during this work phase.
Friday, September 20, 2019
Resurface and Overlay Projects
The contractor worked on Lynn Street this week and was able to get all removals complete, drain tile installed, and the surface brought back to a gravel driving surface. All residents, including Becky Lane, should have access to their driveways by the end of today. The contractor will now be moving to Burton Lane. They will be starting removals on Monday.
Tuesday, September 17, 2019
New pioneer pedestrian bridge
The contractor set the new pioneer pedestrian bridge today between Lake Sisseton and Lake George. The project is still under construction and the bridge is currently closed to pedestrian traffic. Stay tuned for the opening of the newest addition to the City’s trail system.
Winnebago Avenue Reconstruction
The contractor is installing drain tile on phase 1 of the project and will soon start placing the aggregate surface. With good weather, we are hoping to be moving into phase 2 in the next two weeks. When phase 2 begins, traffic control and access to the Five Lakes cooperative mobile home park will be moved to the east entrance. Stay tuned for further information on when that change will occur.
Resurface and Overlay projects
The contractor was able to get started on these projects after last weeks rains. They are completing some storm sewer work on the end of Hengen Street today. The contractor plans to move into Lynn Street on Wednesday, Sept. 18th. They will begin the removal process and access to the homes on Lynn and Becky will be restricted in the next day or two. Please be careful around the construction and plan ahead for access restrictions. Contact City Hall if you have questions about access.
Friday, August 23, 2019
Resurface and Overlay Projects
This year's projects include a resurface of Lynn Street from the dead end to E Interlaken, Burton Lane from N Perimeter to S Perimeter, and the downtown parking lot adjacent to Lake Avenue behind the Human Services building. Additionally, overlays of 4th Street from Prairie to TH 15 and an overlay of the south half of the Day Farm Trail are included in this contract. The overlay of Albion Avenue past Interlaken Golf Course was completed in July. The contractor is expected to begin these projects the week of Labor Day.
Please contact City Hall at 238-9461 if you have questions about these upcoming projects.
Please contact City Hall at 238-9461 if you have questions about these upcoming projects.
Winnebago Avenue Reconstruction
Work is nearing completion on the underground portion of Phase 1. The contractor has the watermain and storm sewer installed and is going to be starting the subgrade excavation on Monday. A couple progress pictures of the pipe installation.
Wednesday, July 24, 2019
Winnebago Avenue Reconstruction
Winnebago Avenue from TH 15 east to the end of the existing pavement is being reconstructed as part of the City's 2019 Improvement Program. The City's contractor is moving onto the project today. Road closures will be getting set up Thursday with the road being closed at Phase 1 beginning Friday. This project will be completed in phases and the closures and access will be adjusted accordingly. See the traffic control and phasing plans below. Traffic for the industrial park will be directed to 10th Street during the project. The project is expected to continue through November 15th. Updates will be provided on this site as the conditions change. Please contact City Hall directly if you have specific questions.
Subscribe to:
Posts (Atom)