All of the concrete walls for the filters are now complete. Concrete is being cast for the new clarifiers and footings for the chemical unloading garage are being formed. The block for the new shallow intake portion of the plant have been installed on the back side of the existing plant and this addition is visible from the lake side. Electrical, mechanical, and plumbing contractors are working all around the plant to install miles of wiring, duct work and process piping. Here are a couple of photos showing the wall of steel being tied for the new clarifier basins and a photo of the south side of the building with the elevator shaft on the left side of the picture.