Friday, June 28, 2013

Elm Street Construction

Elm Street reconstruction is ongoing from 1st Street to the railroad tracks. All existing street has been removed and many houses have been running off temporary water with the removals of the existing sanitary and water main. All new sanitary and water main is now installed from 1st Street to 3rd Street. These houses should have normal water service restored within a week or so. The residents north of 3rd will soon be contacted about having there water set up for temporary service as well. The intersection of 4th Street and Elm is closed and will be at least until the 4th of July. The detour is set up to have traffic use 3rd street as the east/west crossing point of Elm. Here are a couple construction photos.