Water Treatment Plant

The water treatment plant started sending out finished water to the distribution system about two weeks ago. All the systems are running as expected and the contractor is working to finish up the interior spaces as well as starting on some punch list items. The parking lots have been completed and landscaping will begin shortly. The project is scheduled for substantial completion in mid-October. Here are some interior pictures of the operator's room, solids contact basin, softening room, and entry.