Friday, September 26, 2014

Albion Avenue Reconstruction

Concrete paving began this morning at 7am. The sub-contractor for paving is Doyle Conner which is based in Rochester. Here is a look down the street at the grade with all of the dowel baskets set in place for each transverse joint. The second picture shows how the concrete is placed on grade ahead of the paving machine. Lastly, is a photo of first concrete placed this morning. The contractor will be paving approximately 850 cubic yards today.