2017 Improvements

The City's 2017 Improvement program is underway. There are several projects this year all around the City. Visit http://fairmont.org/wp-content/uploads/2017/02/2017-Improvement-Program.pdf to view the complete improvement program.

Margaret Street is scheduled to be upgraded from North Avenue to TH 15. Holtmeier Construction is anticipated to begin in late August or early September. Northdale Construction will be completing the reconstruction of 10th and 11th street from North Avenue west to Lake George and is expected to begin the first week of August.

The resurface and overlay projects being completed by Beemer Companies began last week. Summit and Stade have been milled and the asphalt overlay is currently scheduled for next week. Cardinal and Charles are seeing activity from new sidewalk construction to milling of the existing pavement. These two resurface projects will result in local traffic disruptions, but access to the neighborhood will be maintained during the work. Those along Cardinal and Charles will have a few days of restricted access to the driveways. The contractor is working to minimize these restrictions and affected properties will be notified by the contractor.

All of the seal coat work was completed on July 11th and City crews will begin sweeping up the additional aggregate next week.