2017 Improvements

Beemer Companies is continuing to make progress on the resurface and overlay projects. Stade and Summit overlays were completed last week. Cardinal and Charles have been brought up to gravel grade and paving of those two streets is currently scheduled for the week of 8/14. Camelot Court is currently being excavated and new aggregate and drain tile are being installed. Sidewalk installation continues on Cardinal Street and the grading has begun for sidewalk on East Belle Vue.